EUR 1.2 bilion project financed by the World Bank assuming the reconstruction and extension of hydrotechnical devices, floodbanks and resistance walls which are expected to protect the Wrocław area (South East Poland) against flooding.

  • The Project:  section B3-1 of the project: vinyl sheet piling used as tight wall in floodbanks of the Widawa and the Oder river at the spillway
  • The Product: GW-610/9 from 1.5 to 7.0 m long
  • The amount: 29 000 square m
  • General Contractor: SKANSKA